Assessment, mitigation, and control of potential gas leakage in existing buildings not designed for gas installation in Indonesia

Hermansyah, H. and Hidayat, M.E.N. and Kumaraningrum, A.R. and Yohda, M. and Shariff, A.B.M. (2018) Assessment, mitigation, and control of potential gas leakage in existing buildings not designed for gas installation in Indonesia. Energies, 11 (11). ISSN 19961073

Full text not available from this repository.
Official URL: https://www.scopus.com/inward/record.uri?eid=2-s2....

Abstract

Operational activities of gas pipelines are associated with potential hazards and risks that can potentially lead to pipeline failure, including failure of the gas distribution pipeline in existing buildings. Unfortunately, few studies on risk analysis of the gas distribution pipeline in existing buildings have been published. Therefore, this study was conducted to provide a reference for analyzing the risk of pipeline leakage caused by small-scale leakage, large-scale gas release, and gas pipeline rupture in existing buildings in Indonesia not designed for gas installation. The study was performed using the event tree analysis method. The methodology of this study was initiated by identifying the scenario of the case of small-scale leakage, large-scale gas release, or gas pipeline rupture. Then, pivotal events were identified, an event tree diagram was constructed, the event failure of each pivotal event was determined, and the probability value of the outcome risk was calculated. The risk was evaluated in terms of fire, casualties, and gas released. The results of this study showed the highest risk in each scenario which can result in fire, severe casualties, and light poisoning. The highest risk in the small-scale leak scenario had a probability value of 1.5 � 10-3. In the large-scale gas release scenario, the highest risk had a probability value to incur a fireball, severe casualties, and light gas poisoning of 6.0 � 10-4. In the gas pipeline rupture scenario, the highest risk had a probability value of fireball, severe casualties, and light poisoning of 7.0 � 10-4. The probability value of each risk was reduced by the installation of a gas detector and water sprinkler as a barrier. © 2018 by the authors. Licensee MDPI, Basel, Switzerland.

Item Type: Article
Additional Information: cited By 4
Uncontrolled Keywords: Buildings; Gas hazards; Gas pipelines; Risk analysis; Risk assessment; Risk perception, Event tree analysis; Gas distribution; Operational activity; Pipeline failures; Pipeline leakage; Pipeline rupture; Potential hazards; Water sprinklers, Gases
Depositing User: Mr Ahmad Suhairi UTP
Date Deposited: 09 Nov 2023 16:36
Last Modified: 09 Nov 2023 16:36
URI: https://khub.utp.edu.my/scholars/id/eprint/9814