Determination of inter-stage idle times in scheduling design of a three stage zero wait batch process

Shafeeq, A. and Mutalib, M.I.A. and Amminudin, K.A. and Muhammad, A. (2008) Determination of inter-stage idle times in scheduling design of a three stage zero wait batch process. Journal of Applied Sciences, 8 (9). pp. 1706-1712. ISSN 18125654

Full text not available from this repository.
Official URL: https://www.scopus.com/inward/record.uri?eid=2-s2....

Abstract

The present research proposes a novel approach based on matrix to determine the makespan of a batch process adopting zero wait transfer policy. The proposed approach uses simple mathematical formulae, applied on a matrix representing the batch process recipes according to a selected production sequence. Rearrangement of the matrix rows according to the varied production sequences possible for the specified batch process recipes enables the makespan to be determined for each sequence. Designer is then provided with the production sequence options with its corresponding makespan from which a selection could be made according to the process conditions. © 2008 Asian Network for Scientific Information.

Item Type: Article
Additional Information: cited By 0
Uncontrolled Keywords: Batch process; Idle time; Mathematical formulas; Matrix approach; Process condition; Production sequences; Transfer policies; Zero wait, Production engineering; Scheduling; Scheduling algorithms, Batch data processing
Depositing User: Mr Ahmad Suhairi UTP
Date Deposited: 09 Nov 2023 15:16
Last Modified: 09 Nov 2023 15:16
URI: https://khub.utp.edu.my/scholars/id/eprint/456

Actions (login required)

View Item
View Item